Jordan Village Improvement Project

Share on Facebook Share on Twitter Share on Linkedin Email this link

The Jordan Village Improvement Project is a major undertaking by the Town of Lincoln to rebuild and improve the infrastructure in Jordan Village. The project will include low-impact development construction techniques and features to reduce factors of climate change. The project is expected to encourage active transportation and to enhance the area for residents, businesses and visitors.

For current project updates, see our News Feed below.

View the Before & After Photos of this transformative project!

Project Goals

The Jordan Village Improvement project will create an anchor destination for residents, businesses, and tourists by building a connected and beautified neighbourhood that focuses on safety, complete streets, landscape appeal, and local heritage.

This project will align with several of the Towns plans, including:


Project Highlights

Some of the key improvements this project will bring to Jordan Village include:

  • New signalized intersection at King Street and Nineteenth Street
  • Pedestrian Square at Main Street and King Street
  • Integration with new Jordan Museum and existing commercial district
  • Increased neighbourhood appeal through landscaping and roadway pavers
  • Focus on investing in the local tree canopy
  • Wayfinding pillars and signage
  • Improved decorative streetlighting
  • Dedicated cycling facilities and increased pedestrian connectivity
  • Community parking lot and arrival zone

Project Objectives

Many improvements to the existing infrastructure on Main St., Nineteenth St., Wismer St., and Twenty-First St. will be completed in order to meet the project goals.

These improvements fall under three categories and include:

1. Underground work:

  • New sanitary main servicing Nineteenth Street, Wismer Road and Main Street with the outflow on Twenty-First Street
  • Integration of new stormwater system with “Soil Cell” technology servicing all streets on the project with two (2) outflow areas:
    1. The intersection of Nineteenth Street and Fourth Avenue
    2. Into the existing outflow at Main Street and Twenty-First Street
  • New watermain servicing the area’s residents and businesses

2. Surface work:

  • Construction of new signalized intersection at King and Nineteenth Streets
  • Two (2) new three way stops along Nineteenth Street at Snure Lane and Wismer Street
  • Closing of Main Street’s access to King Street and the creation of pedestrian plaza
  • Combination of hot mix asphalt and roadway pavers for driving surfaces
  • Sidewalk construction on all streets
  • Dedicated cycle-path on both boulevards along Nineteenth Street
  • Two (2) Retaining Wall Systems:
    1. Main Street south Parking Lot
    2. Existing sidewalk along the Valley
  • New street lights on all streets
  • Construction of new roadway across from the Fire Hall - Snure Lane
  • Installation of wayfinding pillars at intersections

3. Aesthetic enhancements:

  • Enhanced electrical and street lighting component complete with ambient lights and wayfinding pillars
  • Extensive tree and shrub planting to enhance the area
  • Reconstruction and Enhancement of Existing Parking lots:
    1. Reconstruction of south parking lot on Main Street
    2. Reconstruction of parking lot next to Fire Hall
    3. New overflow lot behind Fire Hall)
  • Construction of a new road, Snure Lane

Phases of Work

Phase 4C is completed, ahead of schedule. Phase 5 work will commence in April 2024. See the construction updates below for details.

The Jordan Village Improvement Project is a major undertaking by the Town of Lincoln to rebuild and improve the infrastructure in Jordan Village. The project will include low-impact development construction techniques and features to reduce factors of climate change. The project is expected to encourage active transportation and to enhance the area for residents, businesses and visitors.

For current project updates, see our News Feed below.

View the Before & After Photos of this transformative project!

Project Goals

The Jordan Village Improvement project will create an anchor destination for residents, businesses, and tourists by building a connected and beautified neighbourhood that focuses on safety, complete streets, landscape appeal, and local heritage.

This project will align with several of the Towns plans, including:


Project Highlights

Some of the key improvements this project will bring to Jordan Village include:

  • New signalized intersection at King Street and Nineteenth Street
  • Pedestrian Square at Main Street and King Street
  • Integration with new Jordan Museum and existing commercial district
  • Increased neighbourhood appeal through landscaping and roadway pavers
  • Focus on investing in the local tree canopy
  • Wayfinding pillars and signage
  • Improved decorative streetlighting
  • Dedicated cycling facilities and increased pedestrian connectivity
  • Community parking lot and arrival zone

Project Objectives

Many improvements to the existing infrastructure on Main St., Nineteenth St., Wismer St., and Twenty-First St. will be completed in order to meet the project goals.

These improvements fall under three categories and include:

1. Underground work:

  • New sanitary main servicing Nineteenth Street, Wismer Road and Main Street with the outflow on Twenty-First Street
  • Integration of new stormwater system with “Soil Cell” technology servicing all streets on the project with two (2) outflow areas:
    1. The intersection of Nineteenth Street and Fourth Avenue
    2. Into the existing outflow at Main Street and Twenty-First Street
  • New watermain servicing the area’s residents and businesses

2. Surface work:

  • Construction of new signalized intersection at King and Nineteenth Streets
  • Two (2) new three way stops along Nineteenth Street at Snure Lane and Wismer Street
  • Closing of Main Street’s access to King Street and the creation of pedestrian plaza
  • Combination of hot mix asphalt and roadway pavers for driving surfaces
  • Sidewalk construction on all streets
  • Dedicated cycle-path on both boulevards along Nineteenth Street
  • Two (2) Retaining Wall Systems:
    1. Main Street south Parking Lot
    2. Existing sidewalk along the Valley
  • New street lights on all streets
  • Construction of new roadway across from the Fire Hall - Snure Lane
  • Installation of wayfinding pillars at intersections

3. Aesthetic enhancements:

  • Enhanced electrical and street lighting component complete with ambient lights and wayfinding pillars
  • Extensive tree and shrub planting to enhance the area
  • Reconstruction and Enhancement of Existing Parking lots:
    1. Reconstruction of south parking lot on Main Street
    2. Reconstruction of parking lot next to Fire Hall
    3. New overflow lot behind Fire Hall)
  • Construction of a new road, Snure Lane

Phases of Work

Phase 4C is completed, ahead of schedule. Phase 5 work will commence in April 2024. See the construction updates below for details.

  • Jordan Village Construction Update - June 26, 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Recent Work Completed (Previous 2 Weeks):

    • Main Street Phase 4B:
      • Completed installation of storm sewer
      • Completed road excavation of northbound lane
      • Installed electrical ducts for pillars and streetlights
      • Installed watermain
    • Main Street Phase 4C (Preliminary Work – No Road Closure):
      • Watermain service installations, testing, and commissioning
      • 3750 Main Street parking lot construction. The parking lot will remain open during construction, parking spaces will be limited.
    • Nineteenth Street:
      • Installation of decorative streetlight poles
    • Nineteenth Street Public Parking Lot
      • Tree planting and landscaping
      • Installation of street light poles

    Expected Works (June 26 to July 7):

    • Main Street Phase 4B:
      • Watermain service installations, testing, and commissioning
      • Completing road excavation of the southbound lane
    • Main Street Phase 4C:
      • Road closure traffic control and signage to be installed for road closure on July 3,2023. See provided road closure notice and access map for details
      • Installation of watermain from Snure Lane to Phase 4B limit.
    • Nineteenth Street and Public Parking Lot
      • Streetlight installation continues with overhead wiring and pole removal
      • Completing landscaping and addressing deficiencies


    Main Street – Tree TransplantingMain Street – Tree Transplanting

    Main Street – Watermain InstallationMain Street – Watermain Installation

    Public Parking Lot – LandscapingPublic Parking Lot – Landscaping

    3750 Parking Lot – Construction3750 Parking Lot – Construction


    Thank You For Your Patience

    We understand that construction will be disruptive, and we would like to maintain an open line of communication with the public and businesses. We will do our best to address any concerns in a timely manner.

    Contact Information

    Nem Antunovic is the project’s site inspector; he is available on site full-time and may be able to assist you with addressing any immediate concerns.

    Please also feel free to contact the Town’s Project Manager by phone or by email should you have any questions or concerns.

    The general contractor number is also provided below. Rob Goertz is the Project Manager and primary contact for Trenchline and Roads Inc.

    For urgent after-hour inquiries, please phone the Town’s 24-hour Public Works line.

    • Nem Antunovic, Site Inspector – (226) 218-0776
    • Michael Gacnik, Project Manager – (905) 933-8962
    • Rob Goertz, Trenchline and Roads Inc., General Contractor – (905) 563-0075
    • 24-hour Lincoln Public Works Line – (905) 641-0971
  • Jordan Village Construction Update - June 9, 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Recent Work Completed (Previous 2 Weeks):

    • Main Street Phase 4B:
      • Completion of sewer main and laterals
      • Started installation of storm sewer
      • Started road excavation of northbound lane
    • Main Street Phase 4C (Preliminary Work – No Road Closure):
      • Installation of watermain from King Street to Snure Lane
    • Nineteenth Street:
      • Installation of watermain from Snure Lane to King Street
      • Installation of decorative street light poles
    • Public Parking Lot
      • Now open to the public full-time! (paving complete)

    Expected Works (June 9 – June 21):

    • Main Street Phase 4A:
      • Installation of decorative street light poles
    • Main Street Phase 4B:
      • Complete installation of storm sewer
      • Complete road excavation of northbound lane
      • Installation of electrical ducts for pillars and streetlights
    • Main Street Phase 4C (Preliminary Work – No Road Closure):
      • Watermain service installations, testing, and commissioning
      • 3750 Main Street parking lot construction. The parking lot will remain open during construction, parking spaces will be limited.
    • Nineteenth Street:
      • Installation of decorative streetlight poles


    Project Photos:

    Public Parking Lot Now Open! Public Parking Lot - Now Open! Main Street Phase 4A: Decorative Streetlight InstallationMain Street Phase 4A: Decorative Streetlight Installation

    Nineteenth Street Watermain InstallationNineteenth Street Watermain Installation

    Main Street Phase 4B: Sanitary Service InstallationMain Street Phase 4B: Sanitary Service Installation


    Thank You For Your Patience

    We understand that construction will be disruptive, and we would like to maintain an open line of communication with the public and businesses. We will do our best to address any concerns in a timely manner.

    Contact Information

    Nem Antunovic is the project’s site inspector; he is available on site full-time and may be able to assist you with addressing any immediate concerns.

    Please also feel free to contact the Town’s Project Manager by phone or by email should you have any questions or concerns.

    The general contractor number is also provided below. Rob Goertz is the Project Manager and primary contact for Trenchline and Roads Inc.

    For urgent after-hour inquiries, please phone the Town’s 24-hour Public Works line.

    • Nem Antunovic, Site Inspector – (226) 218-0776
    • Michael Gacnik, Project Manager – (905) 933-8962
    • Rob Goertz, Trenchline and Roads Inc., General Contractor – (905) 563-0075
    • 24-hour Lincoln Public Works Line – (905) 641-0971
  • Jordan Village Construction Update - May 26, 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Recent Work Completed (Previous 2 Weeks):

    • Main Street Phase 4A:
      • Reopened to traffic by the end of the day, over 1 month ahead of schedule!
      • Completed surface works including sidewalks, driveway aprons, decorative crosswalk, and asphalt paving.
      • Please note the final lift of asphalt will be paved next spring.
    • Main Street Phase 4B:
      • Completed sanitary sewer main.
      • Ongoing vibration monitoring to verify vibrations caused by construction remain within acceptable limits.
    • Nineteenth Street Public Parking lot:
      • Completed concrete bus drop-off, curb works, and fine grading.

    Expected Works (May 26 – June 9):

    • Main Street Phase 4A:
      • Installation of streetlights
    • Main Street Phase 4B:
      • Sanitary sewer service installations
      • Installation of storm sewer
    • Nineteenth Street Public Parking lot:
      • Parking lot will be open for the weekend in stone. Paving and paint marking is tentatively scheduled for May 29/30 and the parking lot will be closed during working hours.
      • Installation of sidewalks, lighting, and landscaping.
    • Nineteenth Street:
    • Completing landscaping and streetlight installations.

    Project Photos:

    Main Street Pedestrian CrossoverMain Street Pedestrian Crossover

    Main Street Phase 4AMain Street Phase 4A

    Local Businesses and Contractor – Street Opening Barbecue Local Businesses and Contractor – Street Opening Barbecue

    Nineteenth Street Public Parking Lot

    Nineteenth Street Public Parking Lot


    Thank You For Your Patience

    We understand that construction will be disruptive, and we would like to maintain an open line of communication with the public and businesses. We will do our best to address any concerns in a timely manner.

    Contact Information

    Nem Antunovic is the project’s site inspector; he is available on site full-time and may be able to assist you with addressing any immediate concerns.

    Please also feel free to contact the Town’s Project Manager by phone or by email should you have any questions or concerns.

    The general contractor number is also provided below. Rob Goertz is the Project Manager and primary contact for Trenchline and Roads Inc.

    For urgent after-hour inquiries, please phone the Town’s 24-hour Public Works line.

    • Nem Antunovic, Site Inspector – (226) 218-0776
    • Michael Gacnik, Project Manager – (905) 933-8962
    • Rob Goertz, Trenchline and Roads Inc., General Contractor – (905) 563-0075
    • 24-hour Lincoln Public Works Line – (905) 641-0971
  • Jordan Village Construction Update - May 15, 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Recent Work Completed (Previous 2 Weeks):

    • Main Street Phase 4A:
      • Completed road base construction, curbs, and sidewalk
      • Paver stones installed in on-street parking spaces
    • Main Street Phase 4B:
      • Completed road removal
      • Initiated sanitary sewer installation
      • Vibration monitoring boxes have been installed to verify vibrations caused by construction remain within acceptable limits
    • Nineteenth Street Public Parking lot:
      • Installed electrical ducts, grading, and curbs
    • Snure Lane sidewalks completed


    Expected Works (May 15 – May 24):

    • Main Street Phase 4A:
      • Continuation surface works, landscaping, and preparations for paving
    • Main Street Phase 4B:
      • Continue sanitary sewer installation
    • Nineteenth Street Public Parking lot:
      • Complete curbs, concrete bus drop-off, and preparations for paving
      • Reopen full time by May 19 in stone. Paving to be completed week of May 29.
    • Nineteenth Street, streetlight preparations and installation

    Main Street Pavers Installation

    Main Street Curb and Sidewalk Installation

    Public Parking Lot Electrical Ducts

    Public Parking Lot Curb Installation

    Thank You For Your Patience

    We understand that construction will be disruptive, and we would like to maintain an open line of communication with the public and businesses. We will do our best to address any concerns in a timely manner.

    Contact Information

    Nem Antunovic is the project’s site inspector; he is available on site full-time and may be able to assist you with addressing any immediate concerns.

    Please also feel free to contact the Town’s Project Manager by phone or by email should you have any questions or concerns.

    The general contractor number is also provided below. Rob Goertz is the Project Manager and primary contact for Trenchline and Roads Inc.

    For urgent after-hour inquiries, please phone the Town’s 24-hour Public Works line.

    • Nem Antunovic, Site Inspector – (226) 218-0776
    • Michael Gacnik, Project Manager – (905) 933-8962
    • Rob Goertz, Trenchline and Roads Inc., General Contractor – (905) 563-0075
    • 24-hour Lincoln Public Works Line – (905) 641-0971
  • Jordan Village Construction Update - April 27, 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Recent Work Completed (Previous 2 Weeks):

    • Main Street Phase 4A:
      • Completed major underground works including watermain service connections and storm sewer installation
    • Snure Lane boulevards:
      • Treepit installation (Video Link: Stratavault Soil Vault Treepit Explained)
      • Sidewalk installation
    • Nineteenth Street Public Parking lot:
      • Installed electrical ducts
      • Geogrid installation to stabilize subgrade soil
      • Installed granular and earthworks

    Expected Works (April 27 to May 11):

    • Main Street Phase 4A:
      • Road base construction
      • Curb layout
    • Main Street Phase 4B (North of Museum)
      • Initiate sanitary sewer work
    • Complete Construction of Snure Lane boulevards
    • A portion of the Nineteenth Street parking lot will now be open to the public on weekends (Friday at 6pm to Monday at 6am). Construction will continue during the week to complete curbs, fine grading, and asphalt by May 19, 2023 (weather permitting).
    • Nineteenth Street completing landscaping



    Installation of Treepit at Snure LaneInstallation of Treepit at Snure Lane

    Tree Cell Infographic (Stratavault by Citygreen)Tree Cell Infographic (Stratavault by Citygreen)

    Nineteenth Street Public Parking Lot - Electrical WorkNineteenth Street Public Parking Lot - Electrical Work


    Nineteenth Street Public Parking Lot – Geogrid Subgrade stabilizationNineteenth Street Public Parking Lot – Geogrid Subgrade Stabilization


    Main Street Phase 4A - Installation of Storm SewerMain Street Phase 4A - Installation of Storm Sewer

    Thank You For Your Patience

    We understand that construction will be disruptive, and we would like to maintain an open line of communication with the public and businesses. We will do our best to address any concerns in a timely manner.

    Contact Information

    Nem Antunovic is the project’s site inspector; he is available on site full-time and may be able to assist you with addressing any immediate concerns.

    Please also feel free to contact the Town’s Project Manager by phone or by email should you have any questions or concerns.

    The general contractor number is also provided below. Rob Goertz is the Project Manager and primary contact for Trenchline and Roads Inc.

    For urgent after-hour inquiries, please phone the Town’s 24-hour Public Works line.

    • Nem Antunovic, Site Inspector – (226) 218-0776
    • Michael Gacnik, Project Manager – (905) 933-8962
    • Rob Goertz, Trenchline and Roads Inc., General Contractor – (905) 563-0075
    • 24-hour Lincoln Public Works Line – (905) 641-0971

  • Jordan Village Construction Update - April 14, 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Recent Work Completed (Previous 2 Weeks):

    • Continuation of construction on Main Street Phase 4A
    • Primary focus:
      • Commissioning of the watermain
      • Installation and connection of water and sanitary services
      • Removal of the service tunnel
      • Surface work along west boulevard of Nineteenth Street
      • Removal of excess soil at the Nineteenth Street public parking lot

    Expected Works (April 13 to April 27):

    • Final watermain connections for Phase 4A
    • Installation of storm sewer
    • Earthwork and preparation for roadwork
    • Tree cell installation along Snure within boulevard
    • Nineteenth Street public parking lot construction

    Project Photos:

    Water service connections

    Installation of Tree Cells at SnureInstallation of Tree Cells at Snure

    Final watermain connectionsFinal watermain connections


    Final watermain connectionsFinal watermain connections



    Thank You For Your Patience

    We understand that construction will be disruptive, and we would like to maintain an open line of communication with the public and businesses. We will do our best to address any concerns in a timely manner.

    Contact Information

    Nem Antunovic is the project’s site inspector; he is available on site full-time and may be able to assist you with addressing any immediate concerns.

    Please also feel free to contact the Town’s Project Manager by phone or by email should you have any questions or concerns.

    The general contractor number is also provided below. Rob Goertz is the Project Manager and primary contact for Trenchline and Roads Inc.

    For urgent after-hour inquiries, please phone the Town’s 24-hour Public Works line.

    • Nem Antunovic, Site Inspector – (226) 218-0776
    • Michael Gacnik, Project Manager – (905) 933-8962
    • Rob Goertz, Trenchline and Roads Inc., General Contractor – (905) 563-0075
    • 24-hour Lincoln Public Works Line – (905) 641-0971
  • Jordan Village Construction Update - March 31, 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Recent Work Completed (Previous 2 Weeks):

    • Continuation of construction on Main Street Phase 4A
    • Primary focus:
    1. Installation of 300mm watermain along with a hydrant and water services
    2. Installation of sanitary services
    3. Remaining surface work on Nineteenth St.
    4. Form and pour top section of King St. Pillar

    Expected Works (March 30 – April 13):

    • Commissioning and testing of watermain
    • Watermain connection - tentatively planned overnight on March 5 to 6 to limit business disruption
    • Water service connections
    • Removal of the service tunnel
    • Installation of storm sewers

    Installation of 300mm watermain Sidewalk restoration at Nineteenth Street

    Installation of sanitary services King Street Pillar Foundation

    Thank You for Your Patience

    We understand that construction will be disruptive, and we would like to maintain an open line of communication with the public and businesses. We will do our best to address any concerns in a timely manner.

    Contact Information

    Nem Antunovic is the project’s site inspector; he is available on site full-time and may be able to assist you with addressing any immediate concerns.

    Please also feel free to contact the Town’s Project Manager by phone or by email should you have any questions or concerns.

    The general contractor number is also provided below. Rob Goertz is the Project Manager and primary contact for Trenchline and Roads Inc.

    For urgent after-hour inquiries, please phone the Town’s 24-hour Public Works line.

    • Nem Antunovic, Site Inspector – (226) 218-0776
    • Michael Gacnik, Project Manager – (905) 933-8962
    • Rob Goertz, Trenchline and Roads Inc., General Contractor – (905) 563-0075
    • 24-hour Lincoln Public Works Line – (905) 641-0971
  • Jordan Village Construction Update - March 17, 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Recent Work Completed (Previous 2 Weeks):

    • Continuation of construction on Main Street Phase 4A
    • Primary focus:
      • Placement of decorative fence banners
      • Detailed investigation of existing underground services
      • Installation of sanitary sewer mainline and structures
      • Installation of sanitary services


    Expected Works (March 16 – 31):

    • Completion of sanitary works within Phase 4A
    • Installation of watermain
    • Tree removal on Main Street as indicated by “X” paint markings


    Project Photos:

    Placement of decorative fence bannersDecorative fence banners
    Installation of sanitary servicesInstallation of sanitary services


    Installation of sanitary mainlineInstallation of sanitary mainline


    Thank You For Your Patience

    We understand that construction will be disruptive, and we would like to maintain an open line of communication with the public and businesses. We will do our best

    to address any concerns in a timely manner.


    Contact Information

    Nem Antunovic is the project’s site inspector; he is available on site full-time and may be able to assist you with addressing any immediate concerns.

    Please also feel free to contact the Town’s Project Manager by phone or by email should you have any questions or concerns.

    The general contractor number is also provided below. Rob Goertz is the Project Manager and primary contact for Trenchline and Roads Inc.

    For urgent after-hour inquiries, please phone the Town’s 24-hour Public Works line.

    • Nem Antunovic, Site Inspector – (226) 218-0776
    • Michael Gacnik, Project Manager – (905) 933-8962
    • Rob Goertz, Trenchline and Roads Inc., General Contractor – (905) 563-0075
    • 24-hour Lincoln Public Works Line – (905) 641-0971
  • Jordan Village Construction Update - March 6, 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Recent Work Completed (Previous 2 Weeks):

    • Start of construction on Main Street Phase 4A
    • Primary focus:
      • Installation of construction fencing
      • Signage for pedestrians and business
      • Construction of a wheelchair access at the South limit
      • Removal of surface (asphalt, curb & sidewalk)

    Expected Works (March 6– 15):

    • Construction Fence Covers to be installed
    • Continue with Phase 4A surface removals
    • Installation of sanitary mainline from north limit working south

    Project Photos:


    Construction of wheelchair and pedestrian accessConstruction of wheelchair and pedestrian access
    Removal of road surface (Phase 4A)Removal of road surface (Phase 4A)


    Thank You For Your Patience

    We understand that construction will be disruptive, and we would like to maintain an open line of communication with the public and businesses. We will do our best to address any concerns in a timely manner.

    Contact Information

    Nem Antunovic is the project’s site inspector; he is available on site full-time and may be able to assist you with addressing any immediate concerns.

    Please also feel free to contact the Town’s Project Manager by phone or by email should you have any questions or concerns.

    The general contractor number is also provided below. Rob Goertz is the Project Manager and primary contact for Trenchline and Roads Inc.

    For urgent after-hour inquiries, please phone the Town’s 24-hour Public Works line.

    • Nem Antunovic, Site Inspector – (226) 218-0776
    • Michael Gacnik, Project Manager – (905) 933-8962
    • Rob Goertz, Trenchline and Roads Inc., General Contractor – (905) 563-0075
    • 24-hour Lincoln Public Works Line – (905) 641-0971
  • Jordan Village Improvement Project Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    With the warmer weather approaching, the Town’s contractor (Trenchline and Roads Inc.) will be starting the road construction on Main Street in the coming weeks.

    As presented at last year’s Business Open House, Main Street will be completed in three sections to reduce disruption. The first section of construction will be the roadway fronting the Inn On The Twenty and the north commercial building. The road, on-street parking, and lower west sidewalk will be fenced off and closed. The east sidewalk will remain open, and a temporary ramp will be constructed to allow pedestrian access from the parking lot to the west commercial building upper sidewalk.

    Preparations for construction will begin the week of February 20 including some fencing and signage. Main Street is tentatively scheduled to be closed on February 27; formal notices and a media release will follow shortly.

    The Town has ordered decorative fence banners which will be installed in early March. These will be placed in key locations to enhance the aesthetics of the construction fencing and communicate the Open for Business messaging. Signage will also be installed to direct visitors from the parking lot to the temporary ramp.

    We understand that construction will be disruptive, and we would like to maintain an open line of communication with the public and businesses. We will do our best to address any concerns in a timely manner. Nem Antunovic is the project’s site inspector; he is available on site full-time to assist you with addressing any immediate concerns. Please also feel free to contact me at my cell phone number or by email should you have any questions or concerns. For urgent after-hour inquiries, please phone our 24-hour Public Works line.

    • Nem Antunovic, Site Inspector – (226) 218-0776
    • Michael Gacnik, Project Manager – (905) 933-8962
    • Trenchline and Roads Inc, General Contractor – (905) 563-0075
    • 24-hour Lincoln Public Works Line – (905) 641-0971