Jordan Village Construction Update - May 15, 2023

Recent Work Completed (Previous 2 Weeks):

  • Main Street Phase 4A:
    • Completed road base construction, curbs, and sidewalk
    • Paver stones installed in on-street parking spaces
  • Main Street Phase 4B:
    • Completed road removal
    • Initiated sanitary sewer installation
    • Vibration monitoring boxes have been installed to verify vibrations caused by construction remain within acceptable limits
  • Nineteenth Street Public Parking lot:
    • Installed electrical ducts, grading, and curbs
  • Snure Lane sidewalks completed


Expected Works (May 15 – May 24):

  • Main Street Phase 4A:
    • Continuation surface works, landscaping, and preparations for paving
  • Main Street Phase 4B:
    • Continue sanitary sewer installation
  • Nineteenth Street Public Parking lot:
    • Complete curbs, concrete bus drop-off, and preparations for paving
    • Reopen full time by May 19 in stone. Paving to be completed week of May 29.
  • Nineteenth Street, streetlight preparations and installation

Main Street Pavers Installation

Main Street Curb and Sidewalk Installation

Public Parking Lot Electrical Ducts

Public Parking Lot Curb Installation

Thank You For Your Patience

We understand that construction will be disruptive, and we would like to maintain an open line of communication with the public and businesses. We will do our best to address any concerns in a timely manner.

Contact Information

Nem Antunovic is the project’s site inspector; he is available on site full-time and may be able to assist you with addressing any immediate concerns.

Please also feel free to contact the Town’s Project Manager by phone or by email should you have any questions or concerns.

The general contractor number is also provided below. Rob Goertz is the Project Manager and primary contact for Trenchline and Roads Inc.

For urgent after-hour inquiries, please phone the Town’s 24-hour Public Works line.

  • Nem Antunovic, Site Inspector – (226) 218-0776
  • Michael Gacnik, Project Manager – (905) 933-8962
  • Rob Goertz, Trenchline and Roads Inc., General Contractor – (905) 563-0075
  • 24-hour Lincoln Public Works Line – (905) 641-0971
Share Jordan Village Construction Update - May 15, 2023 on Facebook Share Jordan Village Construction Update - May 15, 2023 on Twitter Share Jordan Village Construction Update - May 15, 2023 on Linkedin Email Jordan Village Construction Update - May 15, 2023 link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>