Recent Work Completed (Previous 2 Weeks):
- Main Street Phase 4A:
- Completed major underground works including watermain service connections and storm sewer installation
- Snure Lane boulevards:
- Treepit installation (Video Link: Stratavault Soil Vault Treepit Explained)
- Sidewalk installation
- Nineteenth Street Public Parking lot:
- Installed electrical ducts
- Geogrid installation to stabilize subgrade soil
- Installed granular and earthworks
Expected Works (April 27 to May 11):
- Main Street Phase 4A:
- Road base construction
- Curb layout
- Main Street Phase 4B (North of Museum)
- Initiate sanitary sewer work
- Complete Construction of Snure Lane boulevards
- A portion of the Nineteenth Street parking lot will now be open to the public on weekends (Friday at 6pm to Monday at 6am). Construction will continue during the week to complete curbs, fine grading, and asphalt by May 19, 2023 (weather permitting).
- Nineteenth Street completing landscaping
Thank You For Your Patience
We understand that construction will be disruptive, and we would like to maintain an open line of communication with the public and businesses. We will do our best to address any concerns in a timely manner.
Contact Information
Nem Antunovic is the project’s site inspector; he is available on site full-time and may be able to assist you with addressing any immediate concerns.
Please also feel free to contact the Town’s Project Manager by phone or by email should you have any questions or concerns.
The general contractor number is also provided below. Rob Goertz is the Project Manager and primary contact for Trenchline and Roads Inc.
For urgent after-hour inquiries, please phone the Town’s 24-hour Public Works line.
- Nem Antunovic, Site Inspector – (226) 218-0776
- Michael Gacnik, Project Manager – (905) 933-8962
- Rob Goertz, Trenchline and Roads Inc., General Contractor – (905) 563-0075