Jordan Village Construction Update - March 31, 2023
Recent Work Completed (Previous 2 Weeks):
- Continuation of construction on Main Street Phase 4A
- Primary focus:
- Installation of 300mm watermain along with a hydrant and water services
- Installation of sanitary services
- Remaining surface work on Nineteenth St.
- Form and pour top section of King St. Pillar
Expected Works (March 30 – April 13):
- Commissioning and testing of watermain
- Watermain connection - tentatively planned overnight on March 5 to 6 to limit business disruption
- Water service connections
- Removal of the service tunnel
- Installation of storm sewers
Thank You for Your Patience
We understand that construction will be disruptive, and we would like to maintain an open line of communication with the public and businesses. We will do our best to address any concerns in a timely manner.
Contact Information
Nem Antunovic is the project’s site inspector; he is available on site full-time and may be able to assist you with addressing any immediate concerns.
Please also feel free to contact the Town’s Project Manager by phone or by email should you have any questions or concerns.
The general contractor number is also provided below. Rob Goertz is the Project Manager and primary contact for Trenchline and Roads Inc.
For urgent after-hour inquiries, please phone the Town’s 24-hour Public Works line.
- Nem Antunovic, Site Inspector – (226) 218-0776
- Michael Gacnik, Project Manager – (905) 933-8962
- Rob Goertz, Trenchline and Roads Inc., General Contractor – (905) 563-0075
- 24-hour Lincoln Public Works Line – (905) 641-0971