Jordan Village Construction Update - June 26, 2023
Recent Work Completed (Previous 2 Weeks):
- Main Street Phase 4B:
- Completed installation of storm sewer
- Completed road excavation of northbound lane
- Installed electrical ducts for pillars and streetlights
- Installed watermain
- Main Street Phase 4C (Preliminary Work – No Road Closure):
- Watermain service installations, testing, and commissioning
- 3750 Main Street parking lot construction. The parking lot will remain open during construction, parking spaces will be limited.
- Nineteenth Street:
- Installation of decorative streetlight poles
- Nineteenth Street Public Parking Lot
- Tree planting and landscaping
- Installation of street light poles
Expected Works (June 26 to July 7):
- Main Street Phase 4B:
- Watermain service installations, testing, and commissioning
- Completing road excavation of the southbound lane
- Main Street Phase 4C:
- Road closure traffic control and signage to be installed for road closure on July 3,2023. See provided road closure notice and access map for details
- Installation of watermain from Snure Lane to Phase 4B limit.
- Nineteenth Street and Public Parking Lot
- Streetlight installation continues with overhead wiring and pole removal
- Completing landscaping and addressing deficiencies
Share Jordan Village Construction Update - June 26, 2023 on Facebook
Share Jordan Village Construction Update - June 26, 2023 on Twitter
Share Jordan Village Construction Update - June 26, 2023 on Linkedin
Email Jordan Village Construction Update - June 26, 2023 link