Jordan Village Construction Update - July 21, 2023

Recent Work Completed (Previous 2 Weeks):

  • Main Street Phase 4B:
    • Completed water commissioning and initiated water service connections
    • Completed curb, sidewalk, and road paving
  • Main Street Phase 4C:
    • Completed sanitary sewer installation and service connections
    • Completed 3750 Main Street parking lot retaining wall preparations
    • Completed tree pits
  • Nineteenth Street and Public Parking Lot:
    • Streetlight installation
    • Completed landscaping and addressing deficiencies

Expected Works (July 21 to August 4):

  • Main Street Phase 4B:
    • Complete remaining water service connections and decommission old watermain
    • On-street parking and driveway restorations
  • Main Street Phase 4C:
    • Complete remaining water service connections and decommission old watermain
    • Complete storm sewer installation
    • 3750 Main Street parking lot construction
  • Nineteenth Street and Public Parking Lot:
    • Streetlight installation continues with overhead wiring and pole removal
    • Complete landscaping and address deficiencies

Project Photos:


Main Street Phase 4B – Concrete and Paving CompletionMain Street Phase 4B - Concrete and Paving Completion

Main Street Phase 4C – Tree Pit InstallationMain Street Phase 4C - Tree Pit Installation
Main Street Phase 4C – Sanitary Sewer InstallationMain Street Phase 4C - Sanitary Sewer Installation

Main Street Phase 4C – Sanitary Sewer InstallationMain Street Phase 4B - Watermain Connection

Thank You For Your Patience

We understand that construction will be disruptive, and we would like to maintain an open line of communication with the public and businesses. We will do our best to address any concerns in a timely manner.

Contact Information

Nem Antunovic is the project’s site inspector; he is available on site full-time and may be able to assist you with addressing any immediate concerns.

Please also feel free to contact the Town’s Project Manager by phone or by email should you have any questions or concerns.

The general contractor number is also provided below. Rob Goertz is the Project Manager and primary contact for Trenchline and Roads Inc.

For urgent after-hour inquiries, please phone the Town’s 24-hour Public Works line.

  • Nem Antunovic, Site Inspector – (226) 218-0776
  • Michael Gacnik, Project Manager – (905) 933-8962
  • Rob Goertz, Trenchline and Roads Inc., General Contractor – (905) 563-0075
  • 24-hour Lincoln Public Works Line – (905) 641-0971

Share Jordan Village Construction Update - July 21, 2023 on Facebook Share Jordan Village Construction Update - July 21, 2023 on Twitter Share Jordan Village Construction Update - July 21, 2023 on Linkedin Email Jordan Village Construction Update - July 21, 2023 link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>