Jordan Village Improvement Project
The Jordan Village Improvement Project is a major undertaking by the Town of Lincoln to rebuild and improve the infrastructure in Jordan Village. The project will include low-impact development construction techniques and features to reduce factors of climate change. The project is expected to encourage active transportation and to enhance the area for residents, businesses and visitors.
For current project updates, see our News Feed below.
View the Before & After Photos of this transformative project!
Project Goals
The Jordan Village Improvement project will create an anchor destination for residents, businesses, and tourists by building a connected and beautified neighbourhood that focuses on safety, complete streets, landscape appeal, and local heritage.
This project will align with several of the Towns plans, including:
- Council priorities for a future-fit Lincoln
- Lincoln's Pathway to Prosperity Economic Development Strategy and Plan
- Tourism Strategy and Action Plan: Creating a Prosperous Tourism Sector
- Lincoln's Official Plan
- Corporate Climate Change Adaptation Plan
Project Highlights
Some of the key improvements this project will bring to Jordan Village include:
- New signalized intersection at King Street and Nineteenth Street
- Pedestrian Square at Main Street and King Street
- Integration with new Jordan Museum and existing commercial district
- Increased neighbourhood appeal through landscaping and roadway pavers
- Focus on investing in the local tree canopy
- Wayfinding pillars and signage
- Improved decorative streetlighting
- Dedicated cycling facilities and increased pedestrian connectivity
- Community parking lot and arrival zone
Project Objectives
Many improvements to the existing infrastructure on Main St., Nineteenth St., Wismer St., and Twenty-First St. will be completed in order to meet the project goals.
These improvements fall under three categories and include:
1. Underground work:
- New sanitary main servicing Nineteenth Street, Wismer Road and Main Street with the outflow on Twenty-First Street
- Integration of new stormwater system with “Soil Cell” technology servicing all streets on the project with two (2) outflow areas:
1. The intersection of Nineteenth Street and Fourth Avenue
2. Into the existing outflow at Main Street and Twenty-First Street - New watermain servicing the area’s residents and businesses
2. Surface work:
- Construction of new signalized intersection at King and Nineteenth Streets
- Two (2) new three way stops along Nineteenth Street at Snure Lane and Wismer Street
- Closing of Main Street’s access to King Street and the creation of pedestrian plaza
- Combination of hot mix asphalt and roadway pavers for driving surfaces
- Sidewalk construction on all streets
- Dedicated cycle-path on both boulevards along Nineteenth Street
- Two (2) Retaining Wall Systems:
1. Main Street south Parking Lot
2. Existing sidewalk along the Valley - New street lights on all streets
- Construction of new roadway across from the Fire Hall - Snure Lane
- Installation of wayfinding pillars at intersections
3. Aesthetic enhancements:
- Enhanced electrical and street lighting component complete with ambient lights and wayfinding pillars
- Extensive tree and shrub planting to enhance the area
- Reconstruction and Enhancement of Existing Parking lots:
1. Reconstruction of south parking lot on Main Street
2. Reconstruction of parking lot next to Fire Hall
3. New overflow lot behind Fire Hall) - Construction of a new road, Snure Lane
Phases of Work
Phase 4C is completed, ahead of schedule. Phase 5 work will commence in April 2024. See the construction updates below for details.
The Jordan Village Improvement Project is a major undertaking by the Town of Lincoln to rebuild and improve the infrastructure in Jordan Village. The project will include low-impact development construction techniques and features to reduce factors of climate change. The project is expected to encourage active transportation and to enhance the area for residents, businesses and visitors.
For current project updates, see our News Feed below.
View the Before & After Photos of this transformative project!
Project Goals
The Jordan Village Improvement project will create an anchor destination for residents, businesses, and tourists by building a connected and beautified neighbourhood that focuses on safety, complete streets, landscape appeal, and local heritage.
This project will align with several of the Towns plans, including:
- Council priorities for a future-fit Lincoln
- Lincoln's Pathway to Prosperity Economic Development Strategy and Plan
- Tourism Strategy and Action Plan: Creating a Prosperous Tourism Sector
- Lincoln's Official Plan
- Corporate Climate Change Adaptation Plan
Project Highlights
Some of the key improvements this project will bring to Jordan Village include:
- New signalized intersection at King Street and Nineteenth Street
- Pedestrian Square at Main Street and King Street
- Integration with new Jordan Museum and existing commercial district
- Increased neighbourhood appeal through landscaping and roadway pavers
- Focus on investing in the local tree canopy
- Wayfinding pillars and signage
- Improved decorative streetlighting
- Dedicated cycling facilities and increased pedestrian connectivity
- Community parking lot and arrival zone
Project Objectives
Many improvements to the existing infrastructure on Main St., Nineteenth St., Wismer St., and Twenty-First St. will be completed in order to meet the project goals.
These improvements fall under three categories and include:
1. Underground work:
- New sanitary main servicing Nineteenth Street, Wismer Road and Main Street with the outflow on Twenty-First Street
- Integration of new stormwater system with “Soil Cell” technology servicing all streets on the project with two (2) outflow areas:
1. The intersection of Nineteenth Street and Fourth Avenue
2. Into the existing outflow at Main Street and Twenty-First Street - New watermain servicing the area’s residents and businesses
2. Surface work:
- Construction of new signalized intersection at King and Nineteenth Streets
- Two (2) new three way stops along Nineteenth Street at Snure Lane and Wismer Street
- Closing of Main Street’s access to King Street and the creation of pedestrian plaza
- Combination of hot mix asphalt and roadway pavers for driving surfaces
- Sidewalk construction on all streets
- Dedicated cycle-path on both boulevards along Nineteenth Street
- Two (2) Retaining Wall Systems:
1. Main Street south Parking Lot
2. Existing sidewalk along the Valley - New street lights on all streets
- Construction of new roadway across from the Fire Hall - Snure Lane
- Installation of wayfinding pillars at intersections
3. Aesthetic enhancements:
- Enhanced electrical and street lighting component complete with ambient lights and wayfinding pillars
- Extensive tree and shrub planting to enhance the area
- Reconstruction and Enhancement of Existing Parking lots:
1. Reconstruction of south parking lot on Main Street
2. Reconstruction of parking lot next to Fire Hall
3. New overflow lot behind Fire Hall) - Construction of a new road, Snure Lane
Phases of Work
Phase 4C is completed, ahead of schedule. Phase 5 work will commence in April 2024. See the construction updates below for details.
-
Road Closure Notice - Jordan Village Improvement Project
Share on Facebook Share on Twitter Share on Linkedin Email this linkSnure Lane, Main Street and Wismer Street
Please be advised that beginning Tuesday, April 1, 2024, Snure Lane in Jordan will be fully closed to through traffic. Additionally, Wismer Street and Main Street will be closed following the work on Snure Lane. These closures are required to complete multiple crosswalk installations.
What is closed and when?
- Snure Lane (Nineteenth Street to Main Street)
- April 1 to April 8, 2024 (Weather Permitting)
- Main Street and Wismer Street (Nineteenth Street to Twenty-First Street)
- April 8 to April 15, 2024 (Weather Permitting)
Properties directly within the closure will still have driveway access; however, residents may be occasionally impacted as construction progresses. If your driveway access is blocked temporarily by the construction works, the contractor will notify you in advance. Please see the closure map below for further details.
We apologize for any inconvenience and thank you for your patience and cooperation.
Should you have any questions or concerns, don't hesitate to get in touch with the project team.
- Nem Antunovic, Site Inspector – (226) 218-0776
- Rob Andrea, Project Manager – (905) 563-8205 ext. 251
- Rob Goertz, Trenchline and Roads Inc., General Contractor – (905) 563-0075
- 24-hour Lincoln Public Works Line – (905) 641-0971
- Snure Lane (Nineteenth Street to Main Street)
-
Jordan Village Construction Update - March 25, 2024
Share on Facebook Share on Twitter Share on Linkedin Email this linkProject Location
Jordan Village (Main, Nineteenth, Twenty-First, Wismer and King Streets)
Project Update
Construction activities will begin the week of April 1, 2024 by the contractor, Trenchline & Roads Inc., starting at the intersection of Nineteenth Street and Snure Lane. Project signboards will be installed to highlight the critical aspects of the project and notify passing vehicles that businesses will remain open during construction.
Schedule
Please see the attached Map of Phases to summarize the construction schedule. This project is being completed in phases to reduce the impact on businesses and residents.
- April 2024 to May 2024 | Snure Lane, 21st and Main Street Cross Walk Installation
- May 2024 to June 2024 | 19th Street from Snure Lane to King Street
- June 2024 to August 2024 | King Street Intersection (from east of 19th to west of Main)
These dates are tentative and may be subject to change as construction progresses; however, residents will be kept updated on any schedule changes throughout the project. Speak Up Lincoln will have an updated schedule as the project progresses, and detours will be posted prior to any closures. During these construction phases, expect minimal access to these areas and roads closed. Residents will continue to have access to driveways at the end of each day and coordinated by the contractor in advance of the work.
What to Expect Next
Construction Signs
Signs, traffic cones and detour signage will be placed before construction starts. Before any detours, the Town will distribute notices to residents and businesses in the construction area. We will also send out information to the broader community via social media and post it to the project website.
Crosswalk Construction (Snure Lane, 21st Street and Main Street)
Construction activities are planned to start the week of April 2, 2024, beginning at Snure Lane, Main Street and 21st Street to complete the installation of the pedestrian crosswalks. This work must take place before continuing with construction of Phase 5 on Nineteenth Street/King Street.
King Street Intersection Signalization and Nineteenth Street Reconstruction
Construction activities will continue on Nineteenth Street, south of Snure Lane to the intersection of King Street. Work includes removing existing roadway features, trenching for new water and sewer mains, and installing new roadway curbs, driveways, on-street parking bays, cycle tracks, and sidewalks. In coordination with the Niagara Region, the King Street intersection will be widened and signalized with formal pedestrian crossings. Additionally, a sidewalk will be constructed on the south side of King Street connecting the intersection to St. John’s Drive.
Please note the final layer of asphalt is planned to be placed throughout Jordan toward the end of the project. This is typical for new construction to allow for minor settlements of the base asphalt and deficiency corrections.
Outstanding Work and Deficiency Tracking
We aim to achieve a high standard of quality for all our construction projects. Like any large-scale work, there will likely be a list of deficiencies that need to be addressed before the project is considered complete. Additionally, completed construction work is under a one-year warranty period. Deficiencies such as inadequate workmanship or landscaping issues will be assessed by the construction inspector according to design specifications. Any confirmed deficiencies will be rectified by the contractor. Additionally, before the warranty period expires, the project team will conduct a final walkthrough to identify any remaining issues to be addressed. If you spot something that concerns you, please don’t hesitate to reach out to us. There is a good chance we have already added it to our list of deficiencies for the contractor to address, but we welcome your input in identifying specific issues. Please reach out to either the Site Inspector or Project Manager to ensure your concerns are included in our tracking system.
Garbage Pickup Impacts
Garbage pick-up will be as generally scheduled for property owners during construction. If required, thecontractor will carry recycling and garbage bins to a more accessible pickup location and then return your containers once emptied. The Town asks that property owners please label their garbage bins with their address before construction. Containers that are not labelled may be misplaced during this process. Unmarked bins will be marked with spray paint by the contractor.
Frequently Asked Questions
What are the hours of work for the contractor?
The contractor is limited to working between 7 a.m. and 7 p.m., Monday to Friday, unless special circumstances require night work. If you have concerns about work occurring outside these hours, please contact the Site Inspector or Project Manager for clarification.
How will my garbage pickup be impacted during construction?
Garbage pick-up will generally proceed as scheduled during construction. If necessary, the contractor will relocate recycling and garbage bins to an accessible pickup location and return them once emptied. To avoid any mix-up, we request property owners to label their bins with their address before construction begins. Unlabeled bins may be marked with spray paint by the contractor to prevent misplacement.
How will dust and dirt be controlled during construction?
While construction is active, we expect a certain degree of dust and dirt. We have planned for this and have included provisions for dust control and street sweeping activities to minimize disturbances. In addition, we will work with our contractor to maintain the working area in a neat and organized fashion outside of working hours. We appreciate the community’s patience with any disruptions as we work to revitalize the area.
Will I have access to my home or businesses during construction?
Access to homes and businesses will generally be maintained throughout the construction period. However, there might be short instances when driveways are temporarily blocked by equipment or ongoing work. If you find your driveway blocked, you can speak to the on-site construction staff for immediate assistance. If staff are not available and you have access concerns, please contact the Site Inspector or Project Manager. For urgent issues after hours, you can reach our 24-hour public works line at 905-641-0971. There will be a short period toward the end of construction when curbs and sidewalks are being installed where driveway access will be restricted for a period. In such cases, the contractor will notify property owners a minimum of 48 hours in advance by letter including the dates of the installation. For people requiring special accommodation for a disability, please contact the Site Inspector or Project Manager.
Will I be able to walk through the construction site?
While the site is active for construction, pedestrian access will generally be accommodated. However, we strongly recommend against walking through the site for non-essential reasons. When navigating the construction area, please exercise caution: adhere to warning signs, steer clear of heavy machinery, and maintain visibility with construction workers and vehicles at all times.
Will there be any trees removed as part of this project?
While we have made efforts to maintain existing trees as much as possible through the design process, existing trees that have been identified for removal will be marked with a red “X” by a certified arborist. These trees will be inspected for nests during the nesting season, and identified nests will be safely relocated if required. During construction, tree protection fencing will be installed at critical locations to protect existing trees and roots. The Jordan Village improvement project includes an extensive tree planting and landscaping plan. The project involves planting over 150 new trees and a wide variety of shrubs, perennials, grasses, and vines. If you have concerns regarding trees identified for removal, please get in touch with the Project Manager.
Will there be any service interruptions to my water or power?
While we aim to minimize disruptions, short-term service interruptions may occur as we connect properties to new services. You will receive at least a 48-hour notice prior to any planned interruptions to your power or water supply. Should you experience any unexpected interruptions, please contact the Site Inspector or Project Manager. For urgent issues outside regular working hours, our 24-hour Public Works line is available at 905-641-0971.
What are the paint markings and flags placed around the site?
A necessary part of the construction process is getting locates for all the underground utilities and infrastructure; the law also requires it. Part of this process involves owners of the utilities placing paint and mini flags; however, homeowners and businesses do not need to maintain these markings, as a paper/electronic copy is available to the contractor. Test pits will also be performed to verify the location of utilities at critical crossings. This process minimizes the potential for any damage to existing utilities and infrastructure during the construction phase.
Contact Information
Town of Lincoln:
- Rob Andrea, C.E.T., PMP, Project Manager
- Phone: 905-563-8205 ext. 251
- Email: randrea@lincoln.ca
Town of Lincoln (After-Hours):
For urgent after-hour inquiries, please phone our 24-hour public works line at 905-641-0971.
Contractor (Trenchline & Roads Inc.):
- Rob Goertz, Project Manager
- Phone: 905-563-0075
- Email: tlr@trenchline.ca
Contract Administration and Inspection (Arcadis):
- Nem Antunovic, Senior Inspector
- Phone: 226-218-0775
- Email: nemanja.antunovic@arcadis.com
Keep an eye out for more information as we move forward with this transformational project in Jordan Village. If you have not already done so, check out the Jordan Village Improvement Project on the Speak Up Lincoln public engagement website.
-
Jordan Village Construction Update - November 9, 2023
Share on Facebook Share on Twitter Share on Linkedin Email this linkRecent Work Completed (Previous Month):
- Main Street Phase 4C (King Street to Lincoln Museum):
- Installed roadway and crosswalk paver stones
- General work throughout the project:
- Paving of the driveways, parking bays, and Nineteenth Street cycle track
- Removal of existing street light poles
- Certification and activation of new streetlighting
Expected Works (November 9 to December 9):
- Main Street Phase 4C (King Street to Lincoln Museum):
- Installation of accessibility ramp to the Jordan Tavern
- Installation of slope stabilizing retaining wall at Snure Lane and Main Street
- General work throughout the project:
- Addressing landscaping deficiencies and outstanding work from pole removals
- Paving of driveways and parking bays
- Completing general site cleanup and preparations for winter operations
Project Photos:
Main Street – Pedestrian Plaza
Main Street and Snure Lane – Paver Stone Installation
Main Street Phase 4C – Road Paver Completion
General – Overhead Wiring and Pole Removals
Thank You For Your Patience
We understand that construction will be disruptive, and we would like to maintain an open line of communication with the public and businesses. We will do our best to address any concerns in a timely manner.
Contact Information
Nem Antunovic is the project’s site inspector; he is available on site full-time and may be able to assist you with addressing any immediate concerns.
Please also feel free to contact the Town’s Project Manager by phone or by email should you have any questions or concerns.
The general contractor number is also provided below. Rob Goertz is the Project Manager and primary contact for Trenchline and Roads Inc.
For urgent after-hour inquiries, please phone the Town’s 24-hour Public Works line.
- Nem Antunovic, Site Inspector – (226) 218-0776
- Michael Gacnik, Project Manager – (905) 933-8962
- Rob Goertz, Trenchline and Roads Inc., General Contractor – (905) 563-0075
- 24-hour Lincoln Public Works Line – (905) 641-0971
-
Jordan Village Construction Update - October 13, 2023
Share on Facebook Share on Twitter Share on Linkedin Email this linkRecent Work Completed (Previous 2 Weeks):
- Main Street Phase 4B (Lincoln Museum North):
- Completed additional landscaping
- Main Street Phase 4C (King St to Lincoln Museum):
- Continued installation of pavers
- Wayfinding pillar completed with bench and “Jordan” sign
- Completing additional landscaping
- General work throughout the project:
- Completed electrical installations
Expected Works (October 13 to November 10):
- Main Street Phase 4B (Lincoln Museum North):
- Completing final landscaping and sod
- Paving of driveways and parking bays (Tentative End of October)
- Main Street Phase 4C (King St to Lincoln Museum):
- Continue paver installations along Main St
- Construction of slope stability retaining wall west of Snure Lane
- General work throughout the project:
- Streetlighting activation, and removal of old poles
- Addressing sidewalk and landscaping deficiencies
- Paving cycle track on Nineteenth Street and final layer of asphalt in parking bays (Tentative End of October)
Project Photos:
Main Street Phase 4C – Jordan Wayfinding Pillar
Main Street Phase 4C – Pedestrian Square
Main Street Phase 4C – Road Paver Installation
Nineteenth Street – Streetlighting Electrical Installation
Thank You For Your Patience
We understand that construction will be disruptive, and we would like to maintain an open line of communication with the public and businesses. We will do our best to address any concerns in a timely manner.
Contact Information
Nem Antunovic is the project’s site inspector; he is available on site full-time and may be able to assist you with addressing any immediate concerns.
Please also feel free to contact the Town’s Project Manager by phone or by email should you have any questions or concerns.
The general contractor number is also provided below. Rob Goertz is the Project Manager and primary contact for Trenchline and Roads Inc.
For urgent after-hour inquiries, please phone the Town’s 24-hour Public Works line.
- Nem Antunovic, Site Inspector – (226) 218-0776
- Michael Gacnik, Project Manager – (905) 933-8962
- Rob Goertz, Trenchline and Roads Inc., General Contractor – (905) 563-0075
- 24-hour Lincoln Public Works Line – (905) 641-0971
- Main Street Phase 4B (Lincoln Museum North):
-
Jordan Village Construction Update - September 29, 2023
Share on Facebook Share on Twitter Share on Linkedin Email this linkRecent Work Completed (Previous 3 Weeks):
-
Main Street Phase 4B (Lincoln Museum North): Recent Work Completed (Previous 3 Weeks):
- Installed topsoil and sod
- Museum courtyard space completed
-
Main Street Phase 4C (King St to Lincoln Museum):
- Parking bay and boulevard pavers installed
- Initiated roadway paver installation
- Wayfinding pillar masonry completed
- Landscaping around parking lot perimeter and Main St
-
General work throughout the project:
- Installed pedestrian cross-over at Snure Lane and Nineteenth Street
- Installed additional signage
Expected Works (September 29 to October 13):
-
Main Street Phase 4B (Lincoln Museum North):
- Completing final landscaping and sod
- Paving of driveways and parking bays
-
Main Street Phase 4C (King St to Lincoln Museum):
- Continue paver installations along Main St
- Construction of slope stability retaining wall west of Snure Lane
-
General work throughout the project:
- Streetlighting activation and removal of old poles
- Addressing landscaping deficiencies
Project Photos:
Main Street Phase 4C – Road Paver Installation and Wayfinding Pillar
Main Street Phase 4C – Boulevard Landscaping and Pedestrian Cross-Over
Nineteenth Street Pedestrian Cross-Over
Main Street Phase 4B – Museum Courtyard during Harvest Pioneer Day Event
Thank You For Your Patience
We understand that construction will be disruptive, and we would like to maintain an open line of communication with the public and businesses. We will do our best to address any concerns in a timely manner.
Contact Information
Nem Antunovic is the project’s site inspector; he is available on site full-time and may be able to assist you with addressing any immediate concerns.
Please also feel free to contact the Town’s Project Manager by phone or by email should you have any questions or concerns.
The general contractor number is also provided below. Rob Goertz is the Project Manager and primary contact for Trenchline and Roads Inc.
For urgent after-hour inquiries, please phone the Town’s 24-hour Public Works line.
- Nem Antunovic, Site Inspector – (226) 218-0776
- Michael Gacnik, Project Manager – (905) 933-8962
- Rob Goertz, Trenchline and Roads Inc., General Contractor – (905) 563-0075
- 24-hour Lincoln Public Works Line – (905) 641-0971
-
Main Street Phase 4B (Lincoln Museum North): Recent Work Completed (Previous 3 Weeks):
-
Jordan Village Construction Update - September 8, 2023
Share on Facebook Share on Twitter Share on Linkedin Email this linkRecent Work Completed (Previous 2 Weeks):
-
Main Street Phase 4B (Lincoln Museum North):
- Completed general landscaping
-
Main Street Phase 4C (King St to Lincoln Museum):
- Completed additional curbs and sidewalks
- Installed boulevard and parking pavers
- Completed tree planting and landscaping
- Installed streetlights
- Completed based paving north of Snure Lane
-
General work throughout the project:
- Installation of wayfinding pillar masonry
Expected Works (September 8 to September 29):
- Main Street Phase 4B (Lincoln Museum North):
- Completing final landscaping including sod
- Museum courtyard space to be completed
- Main Street Phase 4C (King St to Lincoln Museum):
- Continue paver installations and landscaping
- Construction of slope stability retaining wall west of Snure Lane
- General work throughout the project:
- Streetlighting activation and removal of old poles
- Wayfinding Pillar Installations
- Installation of Pedestrian Cross-over at Snure Lane and Nineteenth Street
Project Photos:
Main Street Phase 4C - Streetlights and Landscaping
Main Street Phase 4C - Wayfinding Pillar Masonry Installation
Main Street Phase 4B - Museum Courtyard Construction
Main Street Phase 4C - Base Paving North of Snure Lane
Thank You For Your Patience
We understand that construction will be disruptive, and we would like to maintain an open line of communication with the public and businesses. We will do our best to address any concerns in a timely manner.
Contact Information
Nem Antunovic is the project’s site inspector; he is available on site full-time and may be able to assist you with addressing any immediate concerns.
Please also feel free to contact the Town’s Project Manager by phone or by email should you have any questions or concerns.
The general contractor number is also provided below. Rob Goertz is the Project Manager and primary contact for Trenchline and Roads Inc.
For urgent after-hour inquiries, please phone the Town’s 24-hour Public Works line.
- Nem Antunovic, Site Inspector – (226) 218-0776
- Michael Gacnik, Project Manager – (905) 933-8962
- Rob Goertz, Trenchline and Roads Inc., General Contractor – (905) 563-0075
- 24-hour Lincoln Public Works Line – (905) 641-0971
-
Main Street Phase 4B (Lincoln Museum North):
-
Jordan Village Construction Update - August 23, 2023
Share on Facebook Share on Twitter Share on Linkedin Email this linkRecent Work Completed (Previous 2 Weeks):
-
Main Street Phase 4B (Lincoln Museum North):
- Installation of boulevard pavers and landscaping
- Streetlight installation
-
Main Street Phase 4C (King St to Lincoln Museum):
- Completed installation of tree pits
- Completed road excavation, geogrid installation, and underground duct work
- Completed paving of the Main Street parking lot
- Installed curb and sidewalk at Main St south of Snure Lane
- Initiated streetlight installation
-
General work throughout the project:
- Installation of wayfinding pillar frames
Expected Works (August 23 to September 8):
-
Main Street Phase 4B (Lincoln Museum North):
- Continuing landscaping
-
Main Street Phase 4C (King St to Lincoln Museum):
- Form and pour remaining section of the curb
- Installation of road and boulevard pavers
- Installation of streetlights
-
General work throughout the project:
- Nearing completion of streetlighting installation
Project Photos:
Main Street Phase 4C - Large Pillar Frame Installation
Main Street Phase 4C - Parking Lot Paving
Main Street Phase 4C - Tree Pit Installation
Main Street Phase 4C - Curb and Sidewalk Installation
Main Street Phase 4B - Landscaping and Streetlights
Nineteenth Street - Wayfinding Pillar Installation
Thank You For Your Patience
We understand that construction will be disruptive, and we would like to maintain an open line of communication with the public and businesses. We will do our best to address any concerns in a timely manner.
Contact Information
Nem Antunovic is the project’s site inspector; he is available on site full-time and may be able to assist you with addressing any immediate concerns.
Please also feel free to contact the Town’s Project Manager by phone or by email should you have any questions or concerns.
The general contractor number is also provided below. Rob Goertz is the Project Manager and primary contact for Trenchline and Roads Inc.
For urgent after-hour inquiries, please phone the Town’s 24-hour Public Works line.
- Nem Antunovic, Site Inspector – (226) 218-0776
- Michael Gacnik, Project Manager – (905) 933-8962
- Rob Goertz, Trenchline and Roads Inc., General Contractor – (905) 563-0075
- 24-hour Lincoln Public Works Line – (905) 641-0971
-
Main Street Phase 4B (Lincoln Museum North):
-
Jordan Village Construction Update - August 3, 2023
Share on Facebook Share on Twitter Share on Linkedin Email this linkRecent Work Completed (Previous 2 Weeks):
-
Main Street Phase 4B (Lincoln Museum North):
- Completed remaining water service connections and decommissioned old watermain.
- Completed sanitary service cleanout installations.
-
Main Street Phase 4C (King Street to Lincoln Museum):
- A significant milestone – underground infrastructure is now complete, including watermain, storm sewers, and sanitary sewers. Additionally, Jordan Village is now serviced by a complete loop of a new watermain on Main Street and Nineteenth Street.
- Completed 3750 Main Street parking lot retaining wall.
- Completed additional tree pits.
- Initiated road excavation.
-
General:
- Streetlight installation.
- Completing landscaping and addressing deficiencies.
Expected Work (August 3 to August 18):
-
Main Street Phase 4B (Lincoln Museum North):
- Complete paver installation on boulevards.
- Complete on-street parking and driveway restorations.
- Initiate streetlight installation.
-
Main Street Phase 4C (King Street to Lincoln Museum):
- Road excavation and road base installation.
- Streetlight duct installation.
- Curb and sidewalk installation.
- Complete tree pit installations.
-
General:
- Streetlight installation continues.
- Complete landscaping and address deficiencies.
Project Photos:
Main Street Phase 4C - Tree Pit Installations
Main Street Phase 4C - Jordan Village Final Watermain ConnectionMain Street Phase 4C - Road Base Preparation
Main Street Phase 4C - Trenchless Boring Method Used to Protect Trees
Thank You for Your Patience
We understand that construction will be disruptive, and we would like to maintain an open line of communication with the public and businesses. We will do our best to address any concerns in a timely manner.
Contact Information
Nem Antunovic is the project’s site inspector; he is available on site full-time and may be able to assist you with addressing any immediate concerns.
Please also feel free to contact the Town’s Project Manager by phone or by email should you have any questions or concerns.
The general contractor number is also provided below. Rob Goertz is the Project Manager and primary contact for Trenchline and Roads Inc.
For urgent after-hour inquiries, please phone the Town’s 24-hour Public Works line.
- Nem Antunovic, Site Inspector – (226) 218-0776
- Michael Gacnik, Project Manager – (905) 933-8962
- Rob Goertz, Trenchline and Roads Inc., General Contractor – (905) 563-0075
- 24-hour Lincoln Public Works Line – (905) 641-0971
-
Main Street Phase 4B (Lincoln Museum North):
-
Jordan Village Construction Update - July 21, 2023
Share on Facebook Share on Twitter Share on Linkedin Email this linkRecent Work Completed (Previous 2 Weeks):
- Main Street Phase 4B:
- Completed water commissioning and initiated water service connections
- Completed curb, sidewalk, and road paving
- Main Street Phase 4C:
- Completed sanitary sewer installation and service connections
- Completed 3750 Main Street parking lot retaining wall preparations
- Completed tree pits
- Nineteenth Street and Public Parking Lot:
- Streetlight installation
- Completed landscaping and addressing deficiencies
Expected Works (July 21 to August 4):
- Main Street Phase 4B:
- Complete remaining water service connections and decommission old watermain
- On-street parking and driveway restorations
- Main Street Phase 4C:
- Complete remaining water service connections and decommission old watermain
- Complete storm sewer installation
- 3750 Main Street parking lot construction
- Nineteenth Street and Public Parking Lot:
- Streetlight installation continues with overhead wiring and pole removal
- Complete landscaping and address deficiencies
Project Photos:
Thank You For Your Patience
We understand that construction will be disruptive, and we would like to maintain an open line of communication with the public and businesses. We will do our best to address any concerns in a timely manner.
Contact Information
Nem Antunovic is the project’s site inspector; he is available on site full-time and may be able to assist you with addressing any immediate concerns.
Please also feel free to contact the Town’s Project Manager by phone or by email should you have any questions or concerns.
The general contractor number is also provided below. Rob Goertz is the Project Manager and primary contact for Trenchline and Roads Inc.
For urgent after-hour inquiries, please phone the Town’s 24-hour Public Works line.
- Nem Antunovic, Site Inspector – (226) 218-0776
- Michael Gacnik, Project Manager – (905) 933-8962
- Rob Goertz, Trenchline and Roads Inc., General Contractor – (905) 563-0075
- 24-hour Lincoln Public Works Line – (905) 641-0971
- Main Street Phase 4B:
-
Jordan Village Construction Update - July 10, 2023
Share on Facebook Share on Twitter Share on Linkedin Email this linkRecent Work Completed (Previous 2 Weeks):
- Main Street Phase 4B:
- Watermain service installations
- West sidewalk and curb construction
- Completed road excavation of the southbound lane
- Main Street Phase 4C:
- Completed water commissioning and water service connections
- 3750 Main Street parking lot construction
- Nineteenth Street and Public Parking Lot
- Streetlight installation
- Completed landscaping and addressing deficiencies
Expected Works (July 7 to July 21):
- Main Street Phase 4B:
- Watermain commissioning and water service connections
- East sidewalk and curb construction
- Main Street Phase 4C:
- Complete water commissioning and water service connections
- 3750 Main Street parking lot construction
- Sanitary sewer installation and sanitary service connections
- Nineteenth Street and Public Parking Lot
- Streetlight installation continues with overhead wiring and pole removal
- Complete landscaping and addressing deficiencies
Thank You For Your Patience
We understand that construction will be disruptive, and we would like to maintain an open line of communication with the public and businesses. We will do our best to address any concerns in a timely manner.
Contact Information
Nem Antunovic is the project’s site inspector; he is available on site full-time and may be able to assist you with addressing any immediate concerns.
Please also feel free to contact the Town’s Project Manager by phone or by email should you have any questions or concerns.
The general contractor number is also provided below. Rob Goertz is the Project Manager and primary contact for Trenchline and Roads Inc.
For urgent after-hour inquiries, please phone the Town’s 24-hour Public Works line.
- Nem Antunovic, Site Inspector – (226) 218-0776
- Michael Gacnik, Project Manager – (905) 933-8962
- Rob Goertz, Trenchline and Roads Inc., General Contractor – (905) 563-0075
- 24-hour Lincoln Public Works Line – (905) 641-0971
- Main Street Phase 4B:
Project Roadmap
-
Town of Lincoln Council Approval
Jordan Village Improvement Project has finished this stageMarch 2021
-
Request for Pre-qualification (RFPQ)
Jordan Village Improvement Project has finished this stageApril 2021
-
Request for Tender (RFT)
Jordan Village Improvement Project has finished this stageJune 2021
-
Project Awarded to Trenchline & Roads Inc.
Jordan Village Improvement Project has finished this stageSeptember 2021
-
Project Start Date
Jordan Village Improvement Project has finished this stageMarch 10, 2022 - weather permitting
-
Wismer Reconstruction (from 21st to 19th Street)
Jordan Village Improvement Project has finished this stageMarch 2022 - July 2022
-
Nineteenth Street Road Reconstruction
Jordan Village Improvement Project has finished this stageApril 2022 - July 2022
-
Snure Lane Road Reconstruction
Jordan Village Improvement Project has finished this stageSpring 2023
-
Main Street Reconstruction from Twenty-first Street to 150m South
Jordan Village Improvement Project has finished this stageMarch 2023 - June 2023
-
Nineteenth Street Public Parking Lot Reconstruction
Jordan Village Improvement Project has finished this stageFebruary 2023 - May 2023
-
Main Street Reconstruction from 150m South of Twenty-first Street to the Lincoln Museum and Cultural Centre
Jordan Village Improvement Project has finished this stageJune 2023 - August 2023
-
Main Street Reconstruction From Lincoln Musuem and Cultural Centre to King Street
Jordan Village Improvement Project has finished this stageJuly 2023 - December 2023
-
Winter Shutdown
Jordan Village Improvement Project is currently at this stageOur contractor plans for the winter shutdown and has phased construction to minimize disruption over the winter. The next phase is expected to resume in April 2024.
-
King Street Intersection Signalization and Sidewalk Construction
this is an upcoming stage for Jordan Village Improvement ProjectApril 2024 - July 2024
-
Final Layer of Asphalt Paving
this is an upcoming stage for Jordan Village Improvement ProjectYou may have noticed a slight gap between the newly paved asphalt and the concrete curb gutter. This was done intentionally as it is good practice to allow time for the base layer of asphalt to settle. The final layer of asphalt provides a smooth finish at the final grade. This also allows for minimal seams between different phases of construction. As such, the last layer of asphalt will be delayed a minimum of one year to allow for a smooth, seamless finish at the end of the project.
Who's Listening
-
Phone 905-933-8962 Email mgacnik@lincoln.ca
Photos
Public Notices
- JVIP - Before and After Images - Dec 2023 (1.7 MB) (pdf)
- 23-333 JVIP Phase Map Update - Dec 2023 (258 KB) (pdf)
- September 8, 2023 - Construction Update (1.04 MB) (pdf)
- August 23, 2023 - Construction Update (1.04 MB) (pdf)
- August 3, 2023 - Construction Update (1.81 MB) (pdf)
- June 2023 | JVI Access Map (445 KB) (pdf)
- PW - JVIP - Construction Update - December 2023 (2.47 MB) (pdf)
- June 2023 | Project Phase Map (266 KB) (pdf)
- July 10, 2023 | Construction Update (1.83 MB) (pdf)
- June 26, 2023 | Construction Update (1.47 MB) (pdf)
- June 9, 2023 | Construction Update (1.12 MB) (pdf)
- May 26, 2023 | Construction Update (1.37 MB) (pdf)
- May 15, 2023 | Construction Update (1.17 MB) (pdf)
- April 27, 2023 | Construction Update (2.09 MB) (pdf)
- April 14, 2023 | Construction Update (1.11 MB) (pdf)
- March 31, 2023 | Construction Update (1.11 MB) (pdf)
- March 17, 2023 | Construction Update (1.58 MB) (pdf)
- March 6, 2023 | Construction Update (703 KB) (pdf)
- March 2023 | Access Map (253 KB) (pdf)
- March 2023 - NPEI Customer Notification of Notice of Project, Hydro Relocation and Underground Conversion (78.9 KB) (pdf)
- Phase 4A Road Closure Notice | February 27, 2023 (547 KB) (pdf)
- February 2023 - Jordan Village Project - Parking Lot Closure Notice (635 KB) (pdf)
- December 2022 - Project Phases Map.pdf (262 KB) (pdf)
- October 2022 - Community Improvement Update.pdf (1.5 MB) (pdf)
- October 2022 - Project Phases Map.pdf (711 KB) (pdf)
- March 2022 - Sump Pump Notice.pdf (674 KB) (pdf)
- March 2022 - Community Investment Update.pdf (241 KB) (pdf)
- March 2022 - Road Closure Notice.pdf (148 KB) (pdf)
- February 2022 - Map of Project Phases.pdf (1.12 MB) (pdf)
- March 2022 - Project Phase Map.pdf (1.1 MB) (pdf)
- February 2022 - Community Investment Update.docx (157 KB) (docx)
- October 2021 - Community Investment Update.pdf (210 KB) (pdf)
- July 2021 - Public Notice - Sump Pumps Alterations (224 KB) (pdf)
- July 2021- Public Notice - Electrical Hookups (196 KB) (pdf)
- Jordan Village Improvement Project Detour Map.jpg (2.9 MB) (jpg)
Project Frequently Asked Questions
- What are the hours of work for the contractor?
- How will my garbage be impacted during construction?
- How will dust and dirt be controlled during construction?
- Will I have access to my home or businesses during construction?
- Will I be able to walk through the construction site?
- Will there be any trees removed as part of this project?
- Will there be any service interruptions to my water or power?
- What are the paint markings and flags placed around the site?
Additional Information
- Jordan Village Improvements Budget Update Presentation to Council - February 1, 2021 (2.39 MB) (pdf)
- Landscape Plantings for Jordan Village Improvement Project (6.1 MB) (pdf)
- Jordan Village Reconstruction Tender Results (150 KB) (pdf)
- Jordan Village Reconstruction Project Area (156 KB) (pdf)
- OCTOBER 2022 | Phases of work map.pdf (711 KB) (pdf)