Jordan Village Construction Update - September 8, 2023

Recent Work Completed (Previous 2 Weeks):

  • Main Street Phase 4B (Lincoln Museum North):
    • Completed general landscaping
  • Main Street Phase 4C (King St to Lincoln Museum):
    • Completed additional curbs and sidewalks
    • Installed boulevard and parking pavers
    • Completed tree planting and landscaping
    • Installed streetlights
    • Completed based paving north of Snure Lane
  • General work throughout the project:
    • Installation of wayfinding pillar masonry

Expected Works (September 8 to September 29):

  • Main Street Phase 4B (Lincoln Museum North):
    • Completing final landscaping including sod
    • Museum courtyard space to be completed
  • Main Street Phase 4C (King St to Lincoln Museum):
    • Continue paver installations and landscaping
    • Construction of slope stability retaining wall west of Snure Lane
  • General work throughout the project:
    • Streetlighting activation and removal of old poles
    • Wayfinding Pillar Installations
    • Installation of Pedestrian Cross-over at Snure Lane and Nineteenth Street

Project Photos:

Main Street Phase 4C - Streetlights and Landscaping

Main Street Phase 4C - Wayfinding Pillar Masonry Installation

Main Street Phase 4B - Museum Courtyard Construction

Main Street Phase 4C - Base Paving North of Snure Lane


Thank You For Your Patience

We understand that construction will be disruptive, and we would like to maintain an open line of communication with the public and businesses. We will do our best to address any concerns in a timely manner.

Contact Information

Nem Antunovic is the project’s site inspector; he is available on site full-time and may be able to assist you with addressing any immediate concerns.

Please also feel free to contact the Town’s Project Manager by phone or by email should you have any questions or concerns.

The general contractor number is also provided below. Rob Goertz is the Project Manager and primary contact for Trenchline and Roads Inc.

For urgent after-hour inquiries, please phone the Town’s 24-hour Public Works line.

  • Nem Antunovic, Site Inspector – (226) 218-0776
  • Michael Gacnik, Project Manager – (905) 933-8962
  • Rob Goertz, Trenchline and Roads Inc., General Contractor – (905) 563-0075
  • 24-hour Lincoln Public Works Line – (905) 641-0971


Share Jordan Village Construction Update - September 8, 2023 on Facebook Share Jordan Village Construction Update - September 8, 2023 on Twitter Share Jordan Village Construction Update - September 8, 2023 on Linkedin Email Jordan Village Construction Update - September 8, 2023 link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>