Jordan Village Construction Update - November 9, 2023
Recent Work Completed (Previous Month):
- Main Street Phase 4C (King Street to Lincoln Museum):
- Installed roadway and crosswalk paver stones
- General work throughout the project:
- Paving of the driveways, parking bays, and Nineteenth Street cycle track
- Removal of existing street light poles
- Certification and activation of new streetlighting
Expected Works (November 9 to December 9):
- Main Street Phase 4C (King Street to Lincoln Museum):
- Installation of accessibility ramp to the Jordan Tavern
- Installation of slope stabilizing retaining wall at Snure Lane and Main Street
- General work throughout the project:
- Addressing landscaping deficiencies and outstanding work from pole removals
- Paving of driveways and parking bays
- Completing general site cleanup and preparations for winter operations
Project Photos:
Main Street – Pedestrian Plaza
Main Street and Snure Lane – Paver Stone Installation
Main Street Phase 4C – Road Paver Completion
General – Overhead Wiring and Pole Removals
Thank You For Your Patience
We understand that construction will be disruptive, and we would like to maintain an open line of communication with the public and businesses. We will do our best to address any concerns in a timely manner.
Contact Information
Nem Antunovic is the project’s site inspector; he is available on site full-time and may be able to assist you with addressing any immediate concerns.
Please also feel free to contact the Town’s Project Manager by phone or by email should you have any questions or concerns.
The general contractor number is also provided below. Rob Goertz is the Project Manager and primary contact for Trenchline and Roads Inc.
For urgent after-hour inquiries, please phone the Town’s 24-hour Public Works line.
- Nem Antunovic, Site Inspector – (226) 218-0776
- Michael Gacnik, Project Manager – (905) 933-8962
- Rob Goertz, Trenchline and Roads Inc., General Contractor – (905) 563-0075
- 24-hour Lincoln Public Works Line – (905) 641-0971