Jordan Village Construction Update - August 23, 2023
Recent Work Completed (Previous 2 Weeks):
-
Main Street Phase 4B (Lincoln Museum North):
- Installation of boulevard pavers and landscaping
- Streetlight installation
-
Main Street Phase 4C (King St to Lincoln Museum):
- Completed installation of tree pits
- Completed road excavation, geogrid installation, and underground duct work
- Completed paving of the Main Street parking lot
- Installed curb and sidewalk at Main St south of Snure Lane
- Initiated streetlight installation
-
General work throughout the project:
- Installation of wayfinding pillar frames
Expected Works (August 23 to September 8):
-
Main Street Phase 4B (Lincoln Museum North):
- Continuing landscaping
-
Main Street Phase 4C (King St to Lincoln Museum):
- Form and pour remaining section of the curb
- Installation of road and boulevard pavers
- Installation of streetlights
-
General work throughout the project:
- Nearing completion of streetlighting installation
Project Photos:
Main Street Phase 4C - Large Pillar Frame Installation
Main Street Phase 4C - Parking Lot Paving
Main Street Phase 4C - Tree Pit Installation
Main Street Phase 4C - Curb and Sidewalk Installation
Main Street Phase 4B - Landscaping and Streetlights
Nineteenth Street - Wayfinding Pillar Installation
Thank You For Your Patience
We understand that construction will be disruptive, and we would like to maintain an open line of communication with the public and businesses. We will do our best to address any concerns in a timely manner.
Contact Information
Nem Antunovic is the project’s site inspector; he is available on site full-time and may be able to assist you with addressing any immediate concerns.
Please also feel free to contact the Town’s Project Manager by phone or by email should you have any questions or concerns.
The general contractor number is also provided below. Rob Goertz is the Project Manager and primary contact for Trenchline and Roads Inc.
For urgent after-hour inquiries, please phone the Town’s 24-hour Public Works line.
- Nem Antunovic, Site Inspector – (226) 218-0776
- Michael Gacnik, Project Manager – (905) 933-8962
- Rob Goertz, Trenchline and Roads Inc., General Contractor – (905) 563-0075
- 24-hour Lincoln Public Works Line – (905) 641-0971