Jordan Village Construction Update - October 13, 2023

Recent Work Completed (Previous 2 Weeks):

  • Main Street Phase 4B (Lincoln Museum North):
    • Completed additional landscaping
  • Main Street Phase 4C (King St to Lincoln Museum):
    • Continued installation of pavers
    • Wayfinding pillar completed with bench and “Jordan” sign
    • Completing additional landscaping
  • General work throughout the project:
    • Completed electrical installations

Expected Works (October 13 to November 10):

  • Main Street Phase 4B (Lincoln Museum North):
    • Completing final landscaping and sod
    • Paving of driveways and parking bays (Tentative End of October)
  • Main Street Phase 4C (King St to Lincoln Museum):
    • Continue paver installations along Main St
    • Construction of slope stability retaining wall west of Snure Lane
  • General work throughout the project:
    • Streetlighting activation, and removal of old poles
    • Addressing sidewalk and landscaping deficiencies
    • Paving cycle track on Nineteenth Street and final layer of asphalt in parking bays (Tentative End of October)

Project Photos:

Main Street Phase 4C – Jordan Wayfinding Pillar

Main Street Phase 4C – Pedestrian Square

Main Street Phase 4C – Road Paver Installation

Nineteenth Street – Streetlighting Electrical Installation

Thank You For Your Patience

We understand that construction will be disruptive, and we would like to maintain an open line of communication with the public and businesses. We will do our best to address any concerns in a timely manner.

Contact Information

Nem Antunovic is the project’s site inspector; he is available on site full-time and may be able to assist you with addressing any immediate concerns.

Please also feel free to contact the Town’s Project Manager by phone or by email should you have any questions or concerns.

The general contractor number is also provided below. Rob Goertz is the Project Manager and primary contact for Trenchline and Roads Inc.

For urgent after-hour inquiries, please phone the Town’s 24-hour Public Works line.

  • Nem Antunovic, Site Inspector – (226) 218-0776
  • Michael Gacnik, Project Manager – (905) 933-8962
  • Rob Goertz, Trenchline and Roads Inc., General Contractor – (905) 563-0075
  • 24-hour Lincoln Public Works Line – (905) 641-0971
Share Jordan Village Construction Update - October 13, 2023 on Facebook Share Jordan Village Construction Update - October 13, 2023 on Twitter Share Jordan Village Construction Update - October 13, 2023 on Linkedin Email Jordan Village Construction Update - October 13, 2023 link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>