Jordan Village Construction Update - August 3, 2023

Recent Work Completed (Previous 2 Weeks):

  • Main Street Phase 4B (Lincoln Museum North):
    • Completed remaining water service connections and decommissioned old watermain.
    • Completed sanitary service cleanout installations.
  • Main Street Phase 4C (King Street to Lincoln Museum):
    • A significant milestone – underground infrastructure is now complete, including watermain, storm sewers, and sanitary sewers. Additionally, Jordan Village is now serviced by a complete loop of a new watermain on Main Street and Nineteenth Street.
    • Completed 3750 Main Street parking lot retaining wall.
    • Completed additional tree pits.
    • Initiated road excavation.
  • General:
    • Streetlight installation.
    • Completing landscaping and addressing deficiencies.


Expected Work (August 3 to August 18):

  • Main Street Phase 4B (Lincoln Museum North):
    • Complete paver installation on boulevards.
    • Complete on-street parking and driveway restorations.
    • Initiate streetlight installation.
  • Main Street Phase 4C (King Street to Lincoln Museum):
    • Road excavation and road base installation.
    • Streetlight duct installation.
    • Curb and sidewalk installation.
    • Complete tree pit installations.
  • General:
    • Streetlight installation continues.
    • Complete landscaping and address deficiencies.


Project Photos:

Main Street Phase 4C - Tree Pit Installations

Main Street Phase 4C - Jordan Village Final Watermain Connection

Main Street Phase 4C - Road Base Preparation

Main Street Phase 4C - Trenchless Boring Method Used to Protect Trees

Thank You for Your Patience

We understand that construction will be disruptive, and we would like to maintain an open line of communication with the public and businesses. We will do our best to address any concerns in a timely manner.


Contact Information

Nem Antunovic is the project’s site inspector; he is available on site full-time and may be able to assist you with addressing any immediate concerns.

Please also feel free to contact the Town’s Project Manager by phone or by email should you have any questions or concerns.

The general contractor number is also provided below. Rob Goertz is the Project Manager and primary contact for Trenchline and Roads Inc.

For urgent after-hour inquiries, please phone the Town’s 24-hour Public Works line.

  • Nem Antunovic, Site Inspector – (226) 218-0776
  • Michael Gacnik, Project Manager – (905) 933-8962
  • Rob Goertz, Trenchline and Roads Inc., General Contractor – (905) 563-0075
  • 24-hour Lincoln Public Works Line – (905) 641-0971