Jordan Village Construction Update - July 10, 2023
Recent Work Completed (Previous 2 Weeks):
- Main Street Phase 4B:
- Watermain service installations
- West sidewalk and curb construction
- Completed road excavation of the southbound lane
- Main Street Phase 4C:
- Completed water commissioning and water service connections
- 3750 Main Street parking lot construction
- Nineteenth Street and Public Parking Lot
- Streetlight installation
- Completed landscaping and addressing deficiencies
Expected Works (July 7 to July 21):
- Main Street Phase 4B:
- Watermain commissioning and water service connections
- East sidewalk and curb construction
- Main Street Phase 4C:
- Complete water commissioning and water service connections
- 3750 Main Street parking lot construction
- Sanitary sewer installation and sanitary service connections
- Nineteenth Street and Public Parking Lot
- Streetlight installation continues with overhead wiring and pole removal
- Complete landscaping and addressing deficiencies
Thank You For Your Patience
We understand that construction will be disruptive, and we would like to maintain an open line of communication with the public and businesses. We will do our best to address any concerns in a timely manner.
Contact Information
Nem Antunovic is the project’s site inspector; he is available on site full-time and may be able to assist you with addressing any immediate concerns.
Please also feel free to contact the Town’s Project Manager by phone or by email should you have any questions or concerns.
The general contractor number is also provided below. Rob Goertz is the Project Manager and primary contact for Trenchline and Roads Inc.
For urgent after-hour inquiries, please phone the Town’s 24-hour Public Works line.
- Nem Antunovic, Site Inspector – (226) 218-0776
- Michael Gacnik, Project Manager – (905) 933-8962
- Rob Goertz, Trenchline and Roads Inc., General Contractor – (905) 563-0075
- 24-hour Lincoln Public Works Line – (905) 641-0971