Lakeshore Roads and Shoreline Protection Project

Share Lakeshore Roads and Shoreline Protection Project on Facebook Share Lakeshore Roads and Shoreline Protection Project on Twitter Share Lakeshore Roads and Shoreline Protection Project on Linkedin Email Lakeshore Roads and Shoreline Protection Project link

Project Background

In 2022 and 2023, The Town of Lincoln completed two Municipal Class Environmental Assessment (EA) studies to develop long-term solutions to address continued flooding and erosion damage along the Lake Ontario shoreline between Thirty Road and Victoria Avenue. High water levels and isolated flooding events since 2017 have eroded the shoreline and damaged the roads along it significantly.

In addition to needing a solution to halt the long-term erosion of the Lake Ontario shoreline, the affected roadways along it provide access to private property as well public viewing areas of the lakefront and as such are critical to maintain to ensure safe access is available for residents, visitors, and emergency services. Together, the EA studies recommended various solutions to remediate areas along the shoreline and either repair or relocate five local roads including Lakeshore Road, Lakeside Drive, Sandy Cove Drive, Thirty Road and Verity Lane.

Project Description

Both EA’s have produced a preferred solution and the project will be designed and constructed in phases as planned out in the phasing schedule below.

Phasing Solution Description

Construction

Year

Phase 1

Lakeside Drive - Tufford Road to Sann Road

Road Relocation

2024

Phase 2

Lakeshore Road - East of Martin Road

Road Relocation

2025

Phase 3

Lakeshore Road – Martin Road to Cherry Avenue

Road Relocation

2027

Phase 4

Lakeshore Road – Cherry Avenue to Maplegrove Road

Road Relocation

2030

Phase 5

Lakeshore Road – Maplegrove Road to Merritt Road N

Shoreline protection works and minor road improvements

TBA

Phase 6

Verity Lane

Lookout and turnaround on Victoria Ave N

2025

Phase 7

Lakeside Drive – Merritt Road North to Tufford Road

Road Relocation

TBA

Phase 8

Sandy Cove Drive - Sann Road to Bartlett Road

Minor road improvements

TBA

Phase 9

Lookouts

TBA


Proposed Construction Improvements

  • Road Relocation
  • New rural lighting
  • Drainage
  • New driveway locations
  • Shoreline protection
  • Tree planting

The project will align with several of the Town’s plans, including:

Project Background

In 2022 and 2023, The Town of Lincoln completed two Municipal Class Environmental Assessment (EA) studies to develop long-term solutions to address continued flooding and erosion damage along the Lake Ontario shoreline between Thirty Road and Victoria Avenue. High water levels and isolated flooding events since 2017 have eroded the shoreline and damaged the roads along it significantly.

In addition to needing a solution to halt the long-term erosion of the Lake Ontario shoreline, the affected roadways along it provide access to private property as well public viewing areas of the lakefront and as such are critical to maintain to ensure safe access is available for residents, visitors, and emergency services. Together, the EA studies recommended various solutions to remediate areas along the shoreline and either repair or relocate five local roads including Lakeshore Road, Lakeside Drive, Sandy Cove Drive, Thirty Road and Verity Lane.

Project Description

Both EA’s have produced a preferred solution and the project will be designed and constructed in phases as planned out in the phasing schedule below.

Phasing Solution Description

Construction

Year

Phase 1

Lakeside Drive - Tufford Road to Sann Road

Road Relocation

2024

Phase 2

Lakeshore Road - East of Martin Road

Road Relocation

2025

Phase 3

Lakeshore Road – Martin Road to Cherry Avenue

Road Relocation

2027

Phase 4

Lakeshore Road – Cherry Avenue to Maplegrove Road

Road Relocation

2030

Phase 5

Lakeshore Road – Maplegrove Road to Merritt Road N

Shoreline protection works and minor road improvements

TBA

Phase 6

Verity Lane

Lookout and turnaround on Victoria Ave N

2025

Phase 7

Lakeside Drive – Merritt Road North to Tufford Road

Road Relocation

TBA

Phase 8

Sandy Cove Drive - Sann Road to Bartlett Road

Minor road improvements

TBA

Phase 9

Lookouts

TBA


Proposed Construction Improvements

  • Road Relocation
  • New rural lighting
  • Drainage
  • New driveway locations
  • Shoreline protection
  • Tree planting

The project will align with several of the Town’s plans, including:

Comment and Questions Form

We welcome and appreciate questions or comments on this project. Please provide your comment and a staff member will respond as soon as possible.


loader image
Didn't receive confirmation?
Seems like you are already registered, please provide the password. Forgot your password? Create a new one now.
Page last updated: 19 Mar 2024, 12:15 PM