Beamsville Truck Bypass Implementation Study Update

Staff presented the findings and recommendations of the Beamsville Truck Bypass Implementation Study project to the Committee of the Whole on October 18. The report summarized the action items and next steps towards implementing the truck bypass route.

Project Next Steps:

2022 Initiate detailed design and public consultation phase for upgrading both Bartlett Rd and Durham Rd

  • Develop truck bypass route mapping
  • Request Niagara Region to incorporate recommendations in operational and capital plans

2023 Upgrade Durham Rd

2024/2025 Upgrade Bartlett Rd, and Niagara Region to upgrade regional intersections

2025 – Install signage and implement bypass route