Beamsville Truck Bypass Implementation Study Update
Staff presented the findings and recommendations of the Beamsville Truck Bypass Implementation Study project to the Committee of the Whole on October 18. The report summarized the action items and next steps towards implementing the truck bypass route.
Project Next Steps:
2022 – Initiate detailed design and public consultation phase for upgrading both Bartlett Rd and Durham Rd
- Develop truck bypass route mapping
- Request Niagara Region to incorporate recommendations in operational and capital plans
2023 – Upgrade Durham Rd
2024/2025 – Upgrade Bartlett Rd, and Niagara Region to upgrade regional intersections
2025 – Install signage and implement bypass route
For More Information:
- See Staff report PW-32-21
- See Presentation: Beamsville Truck By-Pass Implementation Study Final Report
Share Beamsville Truck Bypass Implementation Study Update on Facebook
Share Beamsville Truck Bypass Implementation Study Update on Twitter
Share Beamsville Truck Bypass Implementation Study Update on Linkedin
Email Beamsville Truck Bypass Implementation Study Update link