Jordan Village Improvement Project Update:

Recent Work Completed:

  • New watermain installed on Wismer Street and Nineteenth Street north of Wismer Street
  • New Sanitary sewer installed and existing sanitary sewer removed on Wismer Street and Nineteenth Street north of Wismer Street
  • Completed removal of existing sewers and curb along Wismer Street and Twenty-First Street

Two-Week Look Ahead:

  • New storm sewer, oil and grit separator, and outlet to be installed on Nineteenth Street north of Wismer Street
  • Water commissioning testing to be completed for new watermain. Please note, residents will be notified 48 hours in advance of any water service interruptions to complete service connections.
  • Installation of new curbs on 21st Street and Wismer

Please feel free to contact me at my cell number, 905-933-8962 or by email should you have any questions or concerns. Please phone our 24-hour public works line for urgent after-hour inquiries at 905-641-0971.

The Town of Lincoln would like to thank all affected residents and businesses for their patience and cooperation during the construction works. Keep an eye out for further email updates as we move forward with this transformational project in the Village.

Regards,


Michael Gacnik

Project Manager, Town of LIncoln