Project Update

The Town of Lincoln is continuing its efforts to address flooding and erosion along the Lake Ontario shoreline between Thirty Road and Victoria Avenue. Following two Municipal Class Environmental Assessment (EA) studies completed in 2022 and 2023, several solutions have been identified to protect the shoreline, mitigate erosion, and ensure safe access for residents and emergency services. The project includes road relocations, shoreline protection works, and infrastructure improvements across multiple phases.

Phase 1A of the project, which focuses on relocating a section of Lakeside Drive, is outlined below. This phase is followed by other improvements planned for Lakeshore Road, Verity Lane, and Sandy Cove Drive over the coming years.

The Town is currently engaging directly with property owners. Stay tuned for updates and more details on how this critical project will help protect our shoreline and local infrastructure.

In 2022 and 2023, The Town of Lincoln completed two Municipal Class Environmental Assessment (EA) studies to develop long-term solutions to address continued flooding and erosion damage along the Lake Ontario shoreline between Thirty Road and Victoria Avenue. High water levels and isolated flooding events since 2017 have eroded the shoreline and damaged the roads along it significantly.

In addition to needing a solution to halt the long-term erosion of the Lake Ontario shoreline, the affected roadways along it provide access to private property as well public viewing areas of the lakefront and as such are critical to maintain to ensure safe access is available for residents, visitors, and emergency services. Together, the EA studies recommended various solutions to remediate areas along the shoreline and either repair or relocate five local roads including Lakeshore Road, Lakeside Drive, Sandy Cove Drive, Thirty Road and Verity Lane.

Both EA’s have produced a preferred solution and the project will be designed and constructed in phases as planned out in the phasing schedule below.

Phasing Solution Description

Construction

Year

Phase 1: Lakeside Drive - Tufford Road to Sann Road

Road Relocation

2024

Phase 2: Lakeshore Road - East of Martin Road

Road Relocation

2025

Phase 3: Lakeshore Road – Martin Road to Cherry Avenue

Road Relocation

2027

Phase 4: Lakeshore Road – Cherry Avenue to Maplegrove Road

Road Relocation

2030

Phase 5: Lakeshore Road – Maplegrove Road to Merritt Road N

Shoreline protection works and minor road improvements

TBA

Phase 6: Verity Lane

Lookout and turnaround on Victoria Ave N

2025

Phase 7: Lakeside Drive – Merritt Road North to Tufford Road

Road Relocation

TBA

Phase 8: Sandy Cove Drive - Sann Road to Bartlett Road

Minor road improvements

TBA
Phase 9: LookoutsTBA


Proposed Construction Improvements

  • Road Relocation
  • New rural lighting
  • Drainage
  • New driveway locations
  • Shoreline protection
  • Tree planting

The project will align with several of the Town’s plans, including:

Provide a short summary of your question.

You have 150 characters left

Provide detailed information relating to your question.

You have 500 characters left

Select a respondent from the list that you would most like to answer your question.

Moderation Policy

These are the people that are listening and responding to your questions.

The Project Team

{{ question.username }} asked

{{question.description}}

{{ answer.respondent.name }}
| Edited

Answer this question

Select the respondent who will be marked as answering the question

Provide the answer to the question. Answer can be saved as draft and published when complete.

No questions found